Description
The Yacaaba Headland project focused on the planning and construction of a walking track from Bennets Beach to the Yacaaba Headland. This involved using a range of techniques including both hand and machine benching, ensuring a sturdy and sustainable trail infrastructure. TRC was assisted in the alignment finalisation by Dave Kirk, a Worramai cultural heritage site officer. Three months into completion of the projects when approximately 50% was completed, a key Indigenous heritage site was discovered which resulted in suspension of the trail development.
All construction was carried out in accordance with the required National Parks and Wildlife Service (NPWS) manual and specifications, along with Worramai cultural members.